WHAT IS A CAPITAL IMPROVEMENTS PLAN
This Plan (CIP) is a blueprint for identifying the City’s capital (infrastructure/equipment) needs, priorities, and estimated costs. The plan also provides viable funding options for these capital projects. The objective of the CIP is to create a logical, transparent, data-driven strategy for investing in the City’s infrastructure needs. The Plan strives to reflect the priorities of City residents and to exemplify sound financial practices.
The CIP process consists of six basic steps:
- * Inventory and evaluation of infrastructure, facilities, and equipment.
- * Advice and guidance from residents on priorities.
- * Prioritization of needs.
- * Identification of funding options to meet the needs.
- * Matching funding sources with improvements.
- * Formal adoption and use by the City Council.
The process provides an orderly and routine method of identifying and financing capital improvements and makes capital expenditures more responsive to the needs of residents by informing and involving them in the process. Thus, the CIP process should ultimately save the City financial resources.
While much of the City’s budget and financial planning efforts are by necessity focused on one or at most two-year intervals, capital planning can still help focus attention on the City’s long-term objectives and financial capacity. This will help balance operating and capital needs. Like many communities in Montana, Havre is often faced with the option of reducing its capital plan objectives in order to balance the operating budget. A formal and adopted capital improvements plan will help to maintain a consistent level of spending for capital needs, barring any unforeseen events.
PROJECT SCHEDULE
PASER Analysis
Start: 10/1/2022 End: 05/15/2023
Kickoff Meeting
Start: 02/13/2023 End: 02/13/2023
Inventories and Information Gathering
Start: 2/14/2023 End: 4/28/2023
Public Outreach Survey
Start: 4/15/2023 End: 5/31/2023
Meeting with City Departments
Start: 5/14/2023 End: 5/19/2023
Department Leads Provide Information
Start: 05/21/2023 End: 06/15/2023
Analysis of Data
Start: 6/15/2023 End: 8/31/2023
Draft CIP
Start: 09/01/2023 End: 10/15/2023
Meet with City on Draft CIP
Start: 10/22/2023 End: 10/27/2023
Public Input on Draft CIP
Start: 11/5/2023 End: 11/30/2023
Final CIP
Start: 12/1/2023 End: 12/31/2023
Project Closeout
Start: 01/01/2024 End: 01/31/2024